pixel
pixelpixelpixel
pixelHome pagepixelpixelAbout uspixelpixelFAQpixelpixelContact uspixelpixelFollow workhealthsafe on Twitterpixelpixelpixelpixelpixel
pixel pixelpixel
pixel
pixel

 Install and concrete RAG bolts safe work method statement/job safety analysis  

The sample RAG bolts safe work method statement / job safety analysis is an extract of the first two identified health and safety hazards associated with how the installation and concreting of RAG bolts.

  • The business logo and administrative details you provide at time of purchase shall replace those that you see in the sample safe work method statement/job safety analysis.

Example RAG bolt installation safe work method statement / job safety analysis

pixel pixel

 Install and concrete RAG bolts safe work method statement  

Installation and concreting of rag bolts

A rag bolt is a foundation bolt having a long tapered head, increasing in size towards its end with jagged points or barbs on its surface to prevent withdrawal under specific conditions.

  • Rag bolts are typically placed in formwork or a bored pier, and cast in-situ e.g. concreted in place;
  • A threaded portion (stud) shall protrude from the concrete surface for the fixing of a structural component.

Tasks

Tasks associated with the installation and concreting of rag bolts would include:
  • Planning and preparation for the excavation (where required), installation and concreting of rag bolts;
  • Establishing an exclusion zone where overhead electrical services and electrical parts are present;
  • Identification as to the nature and location of any underground or overhead services;
  • Identification of asbestos containing materials and products e.g. services pits as per Asbestos Register;
  • Isolation of energised electrical services and electrical parts;
  • Set out the location, position and size of bored pier to be drilled for the installation and concreting of rag bolts;
  • Pre-operational inspection of earthmoving plant and equipment used to drill a bored pier;
  • Set up of earthmoving plant and equipment used to drill a bored pier;
  • Operation and movement of earthmoving plant and equipment in the drilling of a bored pier;
  • Drilling of bored pier with earthmoving plant and equipment;
  • Shoring, benching or battering of trench having depth greater than 1.5 metres or where a hazard is present;
  • Protection of excavation e.g. self-supporting barricade, signage, etc;
  • Select correct type, size, strength, etc, rag bolt as per building designers drawings, specifications and instructions;
  • Erect formwork and falsework where deemed necessary to form the concrete pier retaining the rag bolts;
  • Set and adjust rag bolts to required height;
  • Placement and compaction of concrete using a concrete vibrator;
  • Stripping of formwork and falsework after concrete has cured;
  • Backfilling of work area and compaction of backfill materials;
  • Traffic control requirements when working adjacent to a traffic lane e.g. road closure, blocker vehicle, traffic control person, etc;
  • Safety observer requirements and duties where overhead electrical services and electrical parts are present;
  • Hazardous manual tasks and ergonomic issues associated with the excavation, installation and concreting of rag bolts;
  • Handling, decanting and use of hazardous chemicals;
  • Selection of personal protective equipment (PPE);
  • Conduct a hazard identification of the task being performed;
  • Compliance with specific controls as per a work health and safety regulation, code of practice, standard;
  • Assess risk to workers undertaking the excavation, installation and concreting of rag bolts.
pixel
Person conducting a business or undertaking Electrical Plumbing Group
ABN:
96 147 385 ***
Address of person conducting a business or undertaking:
PO Box ****
Gumdale QLD 4154
Postal address of person conducting a business or undertaking:
PO Box ****
Gumdale QLD 4154
Phone number:
61-7 3823 ****
Fax number:
61-7 3375 ****
Contact person:
Scott *******
Mobile:
04** *** ***
Email:
****@epgi.com.au


 Hazard  
 Risk/outcome  
 Control measures  
 Implementation of controls  
Consultation not undertaken with workers as to the safe method by which rag bolts are to be installed and concreted in-situ.Workers shall be exposed to risk of death, serious injury or illness where the installation and concreting of rag bolts is performed or undertaken incorrectly.

Sustainable injuries would include but not be limited to:

  • First aid medical treatment for cuts and abrasions;
  • Electrocution;
  • Entrapment;
  • Multiple fractures;
  • Crushing injuries;
  • Loss of limb;
  • Skin penetrating injuries;
  • Concrete burns;
  • Respiratory disease;
  • Musculoskeletal injuries; and
  • Permanent disability.

Electrical Plumbing Group shall consult workers as to the method by which the excavation, installation and concreting of rag bolts is undertaken.Electrical Plumbing Group has a duty to ensure the health and safety of themselves, workers and other persons.
  • Workers operating earthmoving plant and equipment for the purpose of drilling bored piers, shall be provided information, instruction, training and supervision as to the correct method by which to undertake the excavation works;
  • Whilst it is not a requirement for workers operating earthmoving equipment to be the holder of a high-risk work licence, a duty is imposed upon Electrical Plumbing Group to assess a person's competency in the operation of earthmoving plant and equipment.

Consultation

Consultation shall occur between line management, workers and health and safety representatives as to the method by which the excavation, installation and concreting of rag bolts shall be undertaken.

The process of consultation shall assess the hazards generated as a result of drilling bored piers, installation and concreting of rag bolts, and take into consideration:

  • A review of all plans, drawing, specifications, etc to identify potential hazards associated with the scope of works;
  • Integrity of ground surface intended to support the mass of earthmoving plant and equipment;
  • Set out of pier to be drilled;
  • Environmental hazards and risks to workers e.g. open excavations, steel starter bars, pits, projections;
  • Operation of earthmoving plant and equipment for the purpose of drilling a bored pier;
  • Pre-operational inspection of plant to assess condition and ensure plant is safe to operate.
  • Movement of earthmoving plant and equipment within an area where excavation works is to be undertaken;
  • Method by which a pier hole shall be drilled using earthmoving plant and equipment;
  • Operation of earthmoving plant and equipment in an established exclusion zone for an overhead electrical service or electrical part;
  • Placement of excavated material relevant to the location and depth of the pier hole, other services, etc;
  • Isolation of hazards within existing services termination pit e.g. electrical cables;
  • Emergency response person where a risk assessment determines that the work is undertaken within an established exclusion zone.
  • Presence of asbestos materials associated with a services termination pit;
  • Erection of formwork and falsework e.g. formatube to encapsulate the in-situ concreting of rag bolts;
  • Installation of rag bolts to a bored pier or formwork and falsework;
  • Set and adjust position and required projection of threaded rag bolts from finished concrete surface;
  • Placement and compaction of concrete to bored pier or formwork and falsework;
  • Stripping of formwork and falsework where required;
  • Prevention of persons, tools, materials, plant, etc falling into pier hole;
  • Establishment of a self-supporting barricade and appropriate signage to forewarn persons of pending hazards;
  • Implementation of permit systems where the performance or undertaking of the task or activity deems such e.g. work, confined space and excavation permits;
  • Hazardous chemicals, substances and products used in the operation of earthmoving plant and equipment, concreting of rag bolts and compaction of concrete;
  • Hazardous manual tasks associated with the drilling of bored piers, installation and concreting of rag bolts;
  • Are persons at risk of serious injury when undertaking the drilling of bored piers, installation and concreting of rag bolts?

Electrical Plumbing Group shall make a prepared for the drilling of bored piers, installation and concreting of rag bolts available for perusal by workers.

Residual risk

Following the implementation of controls the risk should reduce to:

 Hazard  
 Risk/outcome  
 Control measures  
 Implementation of controls  
Introduction of hazards generated from the drilling of bored piers, installation and concreting of rag bolts as a result of implementing proposed control measures. Workers shall be exposed to risk of death, serious injury or illness where hazards are created as a result of implementing proposed control measures.

Sustainable injuries/illnesses would include but not be limited to:

  • First aid medical treatment for cuts and abrasions;
  • Electrocution;
  • Entrapment;
  • Multiple fractures;
  • Crushing injuries;
  • Loss of limb;
  • Skin penetrating injuries;
  • Concrete burns;
  • Respiratory disease;
  • Musculoskeletal injuries; and
  • Permanent disability.

Control measures as per the hierarchy of controls shall be developed and implemented where additional hazards are generated as a result of workers undertaking the drilling of bored piers, installation and concreting of rag bolts.
Electrical Plumbing Group shall ensure hazards generated as a result of drilling of bored piers, and the installation and concreting of rag bolts are identified with the hazard controlled.

Control measures

To prevent risk of death, serious injury or illness to workers and other persons, the person with management or control of the works shall ensure:

  • The risk of death, serious injury or illness resulting due to the conduct of the task is assessed to determine a persons exposure;
  • Control measures to eliminate or minimise the risk of death, serious injury or illness to persons shall be developed in consultation with workers;
  • Control measures as per the hierarchy of controls shall be implemented to prevent, or minimise a persons level of exposure to risk of death, serious injury or illness;
  • Workers undertaking the drilling of bored piers, and the installation and concreting of rag bolts shall be trained as to any new control/s to be implemented and informed as to the hazard notification process should additional hazards be identified.

Residual risk

Following the implementation of controls the risk should reduce to:

 Additional hazards and risks associated with the installation and concreting of RAG bolts  

Additional hazards and risks identified with the installation and concreting of RAG bolts for which control measures have been developed as per the risk identification process include:

  • Workers drilling bored piers and undertaking the installation and concreting of rag bolts without having been involved in the planning process.
  • Plant and equipment used in the drilling of bored piers, installation and concreting of rag bolts.
  • Working with faulty, defective or non-compliant plant.
  • Alteration or modification of plant and equipment.
  • Guards not fitted or installed to plant and equipment.
  • Non-identification as to the location of underground services.
  • Overhead electrical services and electrical parts at a workplace where it is proposed to operate earthmoving plant and equipment.
  • Electrical services and sources within close proximity of where a bored pier is to be drilled.
  • Asbestos containing materials associated with a services termination pit.
  • Setting out position and location of rag bolts.
  • Set up of earthmoving plant for the purpose of undertaking the drilling of a bored pier.
  • Drilling of bored piers.
  • Operation of earthmoving plant and equipment in the drilling of a bored pier.
  • A trench not benched, battered or shored.
  • Erection of formwork and falsework to contain concrete.
  • Installation, set up and adjustment of rag bolts prior to concreting.
  • Placement and discharge of concrete from a concrete truck.
  • Collapse of formwork and falsework during the placement and delivery of concrete.
  • Operation of a concrete vibrator for the consolidation of fresh placed concrete.
  • Exposure to cementitious materials whilst consolidating concrete using a concrete vibrator.
  • Stripping of formwork and falsework.
  • Failure to have a safety observer present.
  • Contact with an energised overhead electric line or a flash-over occurs.
  • Bored pier not filled immediately or protected.
  • Backfilling of excavated area around a pier.
  • Undertaking the installation and concreting of rag bolts adjacent to a traffic lane.
  • Hazardous chemicals and products used in the excavation, installation and concreting of rag bolts.
  • Hazardous manual tasks associated with excavation works, and the installation and concreting of rag bolts.
  • Workers not provided with the required personal protective equipment and having not received instruction as to method by which to wear an article of PPE.
  • Training not provided to workers undertaking excavation works, and the installation and concreting of rag bolts.
  • Housekeeping of a workplace not undertaken and/or no areas assigned for the storage of materials and plant.
  • Workers not advised of specific controls to be implemented to ensure compliance with Work Health and Safety Legislation, Codes of Practice and Standards.
  • Performance of tasks and activities undertaken in connection with the installation and concreting of rag bolts.
  • Failure to monitor the implementation of control measures.

Online SWMS/JSA safe work method statement subscription service

WHS compliance has never been easier with your safe work method statement or job safety analysis prepared by ex WHS Qld Government Workplace Health and Safety Inspectorate in consultation with Industry OHS Representatives to comply with Work Health and Safety Legislation, Codes of Practice, Industry Standards and Australian Standards.

As a subscriber to a WHS online safe work method statement SWMS or job safety analysis JSA you and your employees can:

  • Access and view the work method statement, swms or jsa real time from any web capable device e.g. mobile phone, tablet, laptop, etc (for best results we recommend using the web browser Safari); and
  • Print the safe work method statement, swms or jsa sign off sheet and approval form including change management approval in a pdf format or hard-copy via the print option; and
  • Email the safe work method statement, swms or jsa notification advising a principal contractor, PCBU's and workers as to any specific controls to be implemented at a workplace for which the swms or jsa relates to; and
  • Never worry again about amendments, updates and versions; and
  • WHS maintain one controlled version of the safe work method statement or job safety analysis online as part of our continual improvement process; and
  • That means there can be no confusion as you and your employees are all using the same safe work method statement, swms or jsa at the same time, leaving you to concentrate on your business.

How do you access and implement the safe work method statement or job safety analysis?

To get you online, working, implementing and demonstrating safety compliance management, it's as easy as:

  • Log in via a mobile phone using your username and password;
  • Complete and email the safe work method statement, swms or jsa notification with user access to a principal contractor, PCBU's and workers for a specific workplace; and
  • That's it unless you need to print the sign off sheet, hazard and risk controls or change management approval form.

How do you keep employees and clients current and up to date?

Simple each user be they an employee, contractor or client is assigned a unique username and password to access the controlled version of the installation and concreting of RAG bolts jsa/swms online.

  • Each user can access and view the online swms/jsa from a web capable device e.g. mobile phone with their username and password.
  • Line management personnel can access and print the safe work method statement/job safety analysis and online jsa/swms forms.
  • Line management personnel can send an swms/jsa email notification to a principal contractor, pcbu's and workers advising as to the details of the workplace, principal contractor, commencement and completion dates, person with management or control and any specific controls to be implemented for the installation and concreting of RAG bolts.
  • Users are notified of an amendment to the job safety analysis/work method statement via the online ohs diary and email notification.

What we will do to get you online

As a WHS online safe work method statement or job safety analysis subscriber WHS shall:

  • Create a group user account for your business and assign the user access required by you and your employees.
  • Insert your company logo and business details throughout the online safe work method statement, swms or jsa for the purpose of work health and safety compliance.
  • Notify you if the work method statement or job safety analysis or it's safe operating procedures or methods are amended.

Ordering is simple

  1. Add the safe work method statement, job safety analysis or safe operating procedure and any additional swms's, jsa's or sop's you require to the shopping cart.

  2. Follow the checkout process, ensuring you attach your company logo in a high resolution JPEG format for inclusion in the online safe work method statement/job safety analysis.

  3. Complete your order and payment process. A Tax Invoice will be forwarded to the email address you provide.

What happens next?

Upon receipt of payment notification WHS shall:

  • Send you an email requesting any additional information we may require to create your group registration.
  • Within 2 hours, customise your online safe work method statement/job safety analysis to incorporate your company logo and relevant business details, and create the required subscriber user access and email details of usernames and passwords to you. Where our workload is excessive we reserve the right to extend this time frame to 24 hours.

100% Money back guarantee!!

If you find a more comprehensive online safe work method statement, job safety analysis, safe operating procedure, SWMS, JSA or SOP accessible online, able to be printed and offers an email notification service from any web capable device, and you provide evidence of such we will refund your purchase.

Associated swms's/jsa's

Shoppers buying this safe work method statement/job safety analysis also bought.

pixel
pixel
 Save up to 20% More  
pixel

1 Year online and print access to Install/concrete RAG bolts SWMS/JSA - 5 persons @ $25.00 per user.

more

Total: $125.00 inc GST

1 Year online and print access to Install/concrete RAG bolts SWMS/JSA - 10 persons @ $15.00 per user.

more

Total: $150.00 inc GST

1 Year online and print access to Install/concrete RAG bolts SWMS/JSA - 20 persons @ $9.00 per user.

more

Total: $180.00 inc GST

1 Year online and print access to Install/concrete RAG bolts SWMS/JSA - 30 persons @ $7.00 per user.

more

Total: $210.00 inc GST

1 Year online and print access to Install/concrete RAG bolts SWMS/JSA - 50 persons @ $5.00 per user.

more

Total: $250.00 inc GST

1 Year online and print access to Install/concrete RAG bolts SWMS/JSA - 100 persons @ $3.00 per user.

more

Total: $300.00 inc GST

  • If you require more than 100 users access accounts please Contact us for bulk user discount pricing.

Mini Cart

Click the checkout button to continue
pixel


Return to concreting services

Return to SWMS's/JSA's

pixel
pixel


pixel
pixel
  Login  |  Site Credits